Pier Replacement - Photo Chronology
December 2006 - June 2007
|
|
June 29, 2007
|
|
|
|
|
Pile cap at Bent #7
|
View from Fort Constitution Mines Building
|
|
|
|
|
|
|
Installing guide piles for the floating dock that will be perpendicular to
the end of the pier
|
Electrical switchgear foundation
|
|
|
|
|
June 22, 2007
|
|
|
|
|
View from the cove
|
View from Fort Constitution Mines Building
|
|
|
|
|
|
|
Causeway slab is complete
|
Electrical switchgear foundation
|
|
|
|
|
|
|
Floating dock guide piles at left;
first of the pile caps are formed at Bents 6 and 7.
|
Placing concrete for pile cap at Bent #6
|
|
|
|
|
June 20, 2007
|
|
|
|
|
Forming for pile cap at Bent #7
|
Reinforcing from pile cap down into 30" diameter support pile
|
|
|
|
|
|
|
Sure hope he left himself an "out"
|
Pile cap reinforcing cage in place
|
|
|
|
|
June 8, 2007
|
|
|
|
|
View from the cove
|
View from Fort Constitution Mines Building
|
|
|
|
|
|
|
Causeway . . . all utilities complete
|
Setting temporary frames for setting floating dock guide piles
|
|
|
|
|
June 1, 2007
|
|
|
|
|
View from the cove
|
View from Fort Constitution Mines Building
|
|
|
|
|
|
|
Installing electrical manholes in the causeway
|
Hard at work running electrical conduits toward the pier
|
|
|
|
|
May 25, 2007
|
|
|
|
|
Reinforcing for abutment overlay; note water and sewer penetrations
|
View from Fort Constitution Mines Building
|
|
|
|
|
May 22, 2007
|
|
|
|
|
View from the cove
|
View from Fort Constitution Mines Building
|
|
|
|
|
|
|
Conduits to and from electrical switchgear; pier beyond
|
A new perspective
|
|
|
|
|
May 11, 2007
|
|
|
|
|
View from the cove
|
Rock socketing the last of the 30" diameter support piles
|
|
|
|
|
May 4, 2007
|
|
|
|
|
All but four of the 30" diameter battered piles are now in place
|
View from Fort Constitution Mines Building
|
|
|
|
|
|
|
Sewer manhole and gravity sewer line through pier parking lot
|
Water and sewer piping - pressure testing
|
|
|
|
|
April 27, 2007
|
|
|
|
Feeling a bit under the weather (pun intended) . . . only took one photo
today
|
|
|
|
|
April 20, 2007
|
|
|
|
|
Still remobilizing after the storm; one crane still upriver
|
View from Fort Constitution Mines Building
|
|
|
|
|
April 17, 2007
|
|
|
|
|
Still nasty; barges staying upriver for another day or two
|
View from Fort Constitution Mines Building
|
|
|
|
|
April 16, 2007
|
|
|
|
|
Not a picture of a utility pole; this is the Nor'easter at high tide
|
Another shot of the nasty Nor'easter
|
|
|
|
|
April 13, 2007
|
|
|
|
|
Barges have been moved upriver due to incoming Nor'easter
|
View from Fort Constitution Mines Building
|
|
|
|
|
April 12, 2007
|
|
|
|
|
Utility work under the causeway begins
|
Beyond, rock socketing of the piles continues
|
|
|
|
|
April 6, 2007
|
|
|
|
|
View from the abutment; piles in place through Bent #11 of 17
|
View from Fort Constitution Mines Building
|
|
|
|
|
|
|
Zoomed in from Fort Constitution Mines Building
|
View from the south
|
|
|
|
|
March 30, 2007
|
|
|
|
|
Wide angle view from the south; we now have 3 cranes on-site
|
View from Fort Constitution Mines Building
|
|
|
|
|
|
|
New waterlines have been installed through the pier parking lot
|
Causeway excavated in preparation for new utilities
|
|
|
|
|
March 23, 2007
|
|
|
|
|
Wide angle view from the south
|
View from Fort Constitution Mines Building
|
|
|
|
|
|
|
View from the abutment; piles in place almost to halfway point
|
Threaded stainless steel rebar to support the wave panels
|
|
|
|
|
March 9, 2007
|
|
|
|
|
Epoxy-coated steel reinforcing "cages" for pile caps
|
View from Fort Constitution Mines Building
|
|
|
|
|
|
|
Ten of 36 total support piles in place
|
Temp. work platforms/drive frames beyond half-way point
|
|
|
|
|
March 7, 2007
|
|
|
|
|
Precast concrete "edge beams" at Superior
Concrete in
|
Auburn, Maine . . . ready for shipment when needed on site
|
|
|
|
|
March 1, 2007
|
|
|
|
|
The UNH Facilities office trailer . . . by popular request
|
A beautiful day . . . looking forward to spring
|
|
|
|
|
|
|
Seating/driving first three piles into 2' deep ledge sockets
|
Construction of temp. work platforms/drive frames continues
|
|
|
|
|
February 27, 2007
|
|
|
|
|
"Air-lifting" after having drilled and chiseled 2 feet into ledge
|
View from Fort Constitution Mines Building
|
|
|
|
|
February 22, 2007
|
|
|
|
|
From the south
|
View from Fort Constitution Mines Building
|
|
|
|
|
|
|
Piles in drive frames at Bents #2 through #5, from south
|
Piles in drive frames at Bents #2 through #5, from east
|
|
|
|
|
February 20, 2007
|
|
|
|
|
From the south
|
View from Fort Constitution Mines Building
|
|
|
|
|
|
|
Fabricating temporary drive frame
|
Drilling pocket in ledge, into which pile will seat
|
|
|
|
|
February 16, 2007
|
|
|
|
|
Regrouping after Valentines Day nor'easter
|
View from Fort Constitution Mines Building
|
|
|
|
|
|
|
Work platform constructed to Bent #5
|
Forms for pile caps await installation
|
|
|
|
|
February 9, 2007
|
|
|
|
|
Final sweep of bottom
|
View from Fort Constitution Mines Building
|
|
|
|
|
|
|
Approach trestle
|
Pile socketing operations underway
|
|
|
|
|
February 6, 2007
|
|
|
|
|
Removing the last of the old pier
|
View from Fort Constitution Mines Building
|
|
|
|
|
|
|
Drilling dowels into existing walls for new concrete overlay
|
Preparing to clean out interior of piles
|
|
|
|
|
February 2, 2007
|
|
|
|
|
New work begins . . . Approach trestle piles in drive frames
|
View from Fort Constitution Mines Building
|
|
|
|
|
|
|
Approach trestle
|
Two lonely cribs waiting to be removed
|
|
|
|
|
January 30, 2007
|
|
|
|
|
Handling new piles on crane barge
|
View from Fort Constitution Mines Building
|
|
|
|
|
|
|
Removing cribs
|
12 3/4" guide piles for floating docks
|
|
|
|
|
January 26, 2007
|
|
|
|
|
Extremely cold and windy day
|
View from Fort Constitution Mines Building
|
|
|
|
|
|
|
Setting drive frames and work platform for approach trestle
|
Four more cribs to be removed
|
|
|
|
|
January 19, 2007
|
|
|
|
|
Crib removal underway
|
View from Fort Constitution Mines Building
|
|
|
|
|
|
|
Disassembling a crib prior to transport up river
|
Two cranes and a large excavator are now on site
|
|
|
|
|
January 12, 2007
|
|
|
|
| Removing final
section of original pier deck at abutment
|
View from Fort
Constitution Mines Building
|
|
|
|
|
|
| Off-loading
materials at State Pier staging area
|
30" diameter
pipe piles for new pier
|
|
|
|
|
January 2, 2007
|
|
|
|
| Project Sign
awaiting erection
|
Pier removals
continue, now with two cranes
|
|
|
|
|
|
| Original pier sans
deck
|
Approximately
one-third of deck has been removed
|
|
|
|
|
December 15, 2006
|
|
|
|
| Old
fendering timbers waiting to be off-loaded at the State Pier
|
Sharing the
water with U.S. Coast Guard dredging contractor
|
|
|
|
|
|
|
Grabbing first
piece of existing deck for removal
|
Lifting first
piece of existing deck
|
|
|
|
|
|
| Swinging
first piece of existing deck to barge
|
Grabbing
the next piece of existing deck . . . and so on
|
|
|
|
|