UNH  Pier Facility



Home | General Information | Project Status |Project Documents | Photo & Image Galleries  

Project Status

March 7, 2008

Pier . . .

  1. Project is essentially complete.  Recently, power and site/pier lighting have been turned on.

  2. Remaining items to be completed include installation of a properly sized security gate, some miscellaneous electrical work, general start-up and performance testing of the jib crane, sewer pumps, etc. and general punchlist work some of which is pending spring weather.

  3. UNH researchers are utilizing pier; however, vessels really cannot berth at the pier until power is available on the floating docks.

  4. A U.S. Coast Guard vessel recently berthed at the pier overnight, waiting to escort an LNG tanker into port.

  5. The NOAA SWATH research vessel, which will be home-ported at the UNH pier, is expected in spring of 2009.

Pier Support Facility & Site Utilities . . .

  1. Majority of on-site underground utility work (i.e. water, sewer, storm drainage, electrical & communications ductbanks) is complete.

  2. PSNH have moved their utilities into the new underground ductbank system and swapped over the Coast Guard services to the new feeds.  We are waiting for Comcast to do the same so we can remove the old overhead lines that run across the Town Landing and the UNH cove.

  3. The foundation for barn structure with public restrooms is complete.  Effort is now shifting to the foundation for the bulk feed storage building.

  4. After a long, hard winter, things should start to move a bit more quickly now.

 

FACILITIES DESIGN AND CONSTRUCTION
22 Colovos Road    Durham, New Hampshire   03824-3515
Voice: 603-862-4452    Fax: 603-862-3927

Copyright 2007, The University of New Hampshire, Durham, NH 03824
UNH is part of the University System of New Hampshire.